 Ireo Skyon - PAYMENT PLAN

PAYMENT PLANS

TOWER B

LINKED STAGES

CHARGE

AT THE TIME OF BOOKING 10% BSP
WITHIN 45 DAYS OF BOOKING 10% BSP
COMMENCEMENT OF EXCAVATION 7.5 % BSP + 50 % EDC
CASTING OF BASEMENT ROOF SLAB 7.5 % BSP + 50 % EDC
CASTING OF 1ST FLOOR SLAB 7.5 % BSP + 50 % IDC + 50% PLC
CASTING OF 8TH FLOOR ROOF SLAB 7.5 % BSP + 50 % IDC + 50% PLC
CASTING OF 16TH FLOOR ROOF SLAB 7.5 % BSP + 50 % PARKING
CASTING OF 24TH FLOOR SLAB 7.5 % BSP + 50 % PARKING
CASTING OF 30TH FLOOR SLAB 7.5 % BSP
CASTING OF 36TH FLOOR SLAB 7.5 % BSP
CASTING OF TOP FLOOR SLAB 7.5 % BSP
ON COMPLETION OF STONE/TILE FLOORING IN APARTMENT 7.5 % BSP
*ON OFFER OF POSSESSION 5%BSP + RFMS
*STAMP DUTY & REGISTRATION CHARGES SHALL BE PAYABLE ALONG WITH THE LAST INSTALLMENT

G+8

LINKED STAGES

CHARGE

AT THE TIME OF BOOKING 10% BSP
WITHIN 45 DAYS OF BOOKING 10% BSP
COMMENCEMENT OF EXCAVATION 10 % BSP + 50 % EDC
CASTING OF BASEMENT ROOF SLAB 10 % BSP + 50 % EDC
CASTING OF GROUND FLOOR ROOF SLAB 10 % BSP + 50 % IDC+ 50% PLC
CASTING OF 2ND FLOOR ROOF SLAB 10 % BSP + 50 % IDC+ 50% PLC
CASTING OF 4TH FLOOR ROOF SLAB 10 % BSP + 50 % PARKING
CASTING OF 6TH FLOOR ROOF SLAB 10 % BSP + 50 % PARKING
CASTING OF TOP FLOOR ROOF SLAB 10 % BSP
ON COMPLETION OF STONE/TILE FLOORING IN APARTMENT 5 % BSP
*ON OFFER OF POSSESSION 5%BSP + RFMS
*STAMP DUTY & REGISTRATION CHARGES SHALL BE PAYABLE ALONG WITH THE LAST INSTALLMENT

G+10

LINKED STAGES

CHARGE

AT THE TIME OF BOOKING 10% BSP
WITHIN 45 DAYS OF BOOKING 10% BSP
COMMENCEMENT OF EXCAVATION 10 % BSP + 50 % EDC
CASTING OF BASEMENT ROOF SLAB 10 % BSP + 50 % EDC
CASTING OF 2ND FLOOR ROOF SLAB 10 % BSP + 50 % IDC+ 50% PLC
CASTING OF 4TH FLOOR ROOF SLAB 10 % BSP + 50 % IDC+ 50% PLC
CASTING OF 6TH FLOOR ROOF SLAB 10 % BSP + 50 % PARKING
CASTING OF 8TH FLOOR ROOF SLAB 10 % BSP + 50 % PARKING
CASTING OF TOP FLOOR ROOF SLAB 10 % BSP
ON COMPLETION OF STONE/TILE FLOORING IN APARTMENT 5 % BSP
*ON OFFER OF POSSESSION 5%BSP + RFMS
*STAMP DUTY & REGISTRATION CHARGES SHALL BE PAYABLE ALONG WITH THE LAST INSTALLMENT

G+12

LINKED STAGES

CHARGE

AT THE TIME OF BOOKING 10% BSP
WITHIN 45 DAYS OF BOOKING 10% BSP
COMMENCEMENT OF EXCAVATION 10 % BSP + 50 % EDC
CASTING OF BASEMENT ROOF SLAB 10 % BSP + 50 % EDC
CASTING OF 2ND FLOOR ROOF SLAB 10 % BSP + 50 % IDC+ 50% PLC
CASTING OF 5TH FLOOR ROOF SLAB 10 % BSP + 50 % IDC+ 50% PLC
CASTING OF 8TH FLOOR ROOF SLAB 10 % BSP + 50 % PARKING
CASTING OF 10TH FLOOR ROOF SLAB 10 % BSP + 50 % PARKING
CASTING OF TOP FLOOR ROOF SLAB 10 % BSP
ON COMPLETION OF STONE/TILE FLOORING IN APARTMENT 5 % BSP
*ON OFFER OF POSSESSION 5%BSP + RFMS
*STAMP DUTY & REGISTRATION CHARGES SHALL BE PAYABLE ALONG WITH THE LAST INSTALLMENT